Zirakpur underpass work tardy, set to skip October deadline

Earlier missed August 3 target | Likely to complete by year-end

Show comments

Tribune News Service

Gaurav Kanthwal

Zirakpur, October 2

The under-construction vehicular underpass near the Chandigarh-Zirakpur border is set to miss its second deadline even as the road users continue to face daily harassment owing to snarl-ups amid a bumpy ride on a daily basis.

The travel time from Chandigarh to Zirakpur has stretched from 25 minutes to nearly an hour or more during office hours but the Punjab Public Works Department (PWD) seems unmindful of their plight.

The project missed its first deadline in August. The tentative date for completion of construction work was August 3. The deadline was set for end of October, but going by the ongoing pace of work, the second target date is likely to be missed.

Officials said only if the work was done at an express pace would they be able to reach near completion around Diwali. In all likelihood, the construction work was going to stretch till year-end.

With more than one lakh people in Zirakpur and peripheral areas already grappling with traffic woes due to the underpass, work on another one and two flyovers is set to start at two more places - K-Area and Singhpura Chowk.

The service lanes near the Singhpura Chowk have been cleared and the main work on two flyovers will begin soon. At K-Area, near Baltana, work on an underpass is in the soil-testing stage.

At the Zirakpur underpass, one portion of the ramp towards the Chandigarh side is being filled with earth, which will be followed by setting process. Once the earth is settled, road metalling work will begin.

In the past two months, concrete tiles have been prepared at the site. The retaining wall of one side of the ramp has been erected and earth filled. The earth is being compressed and settled after which road will be made. While one side of the ramp is ready, work on the other side is taking a bit longer.

Zirakpur traffic incharge Rajpal Singh said: "In the past one year, the traffic police have been on toes to ease the bottleneck. We are doing our best. The situation will normalise after the underpass is complete and made operational."

Two-month progress report

Aug 2

Finished: Construction of underpass, retaining wall on the Zirakpur side

Still on: Work on making concrete tiles near Chandigarh end of the ramp

Yet to begin: Work on retaining wall at Chandigarh end

Oct 2

Finished: Work on tiles, earth filling, part of retaining wall on Chandigarh side

Still on: Work on retaining wall, earth filling, compressing at UT end of ramp

Yet to begin: Road metalling on both sides

Reasons for delay

  • Owing to monsoon, slush and labour shortage resulted in tardy pace of construction work
  • Earlier, PWD officials had said rising sand rates and shortage of earth due to mining restrictions had led to delay

Road closed today

Due to recarpeting work, the V3 road between Sectors 6 and 7 will be closed on October 3 and 4. The MC has requested commuters to take alternative routes.

About The Author

The Tribune News Service brings you the latest news, analysis and insights from the region, India and around the world. Follow the Tribune News Service for a wide-ranging coverage of events as they unfold, with perspective and clarity.

#Zirakpur

Show comments
Show comments

Trending News

Also In This Section


Top News


View All

10-year-old Delhi boy runs food cart to support family after father’s death; businessman offers help

Sharing a video on X, Anand Mahindra extends support to the boy

Indian-origin astronaut Sunita Williams set to fly into space again on first crewed mission of Boeing's Starliner

Williams, 59, a retired US Navy captain, and Wilmore will pilot the flight

Gurbani rings out at UK Parliament complex for Baisakhi

The event is organised by the British Indian think-tank 1928 Institute and diaspora membership organisations City Sikhs and the British Punjabi Welfare Association


Most Read In 24 Hours