Ballabgarh Metro Rail won’t open this Diwali

FARIDABAD: The 3.2-km-long stretch of the Metro Rail from Escorts-Mujesar station here to Ballabgarh is unlikely to open before Diwali, as speculated earlier.

Show comments

Jendra Ahlawat

Tribune News Service

Faridabad, October 10

The 3.2-km-long stretch of the Metro Rail from Escorts-Mujesar station here to Ballabgarh is unlikely to open before Diwali, as speculated earlier.

It may be delayed till mid-December due to hassles regarding allotment of parking space at one of the stations and removal of some constructions located very close to the Metro rail line in Ballabgarh city.

The Delhi Metro Rail Corporation (DMRC) authorities have asked HUDA (HSVP) officials to hand over a patch of 2.5 acres situated opposite the NCB (Sant Surdass) Metro station for the construction of the parking lot of the station.

The spot located across National Highway-2 (western side) is presently occupied by 250 shanties and the place is known as Azad Nagar.

Though an attempt was made to clear the constructions here, it is reported that the officials concerned were directed to rehabilitate the residents of this locality in Ashiana housing scheme before taking any action.

“The operation of the Ballabgarh Metro will not be possible before the completion of the work on every segment which includes the construction of the parking lot at the NCB station,” said a DMRC official on condition of anonymity. Claiming that finishing work on the two stations had been going on and was expected to be over in November, he said no date has been fixed for its opening so far.

“We have invited applications from the residents for getting them shifted to the Ashiana scheme where they will get flats constructed by HUDA,” said Estate Officer, HUDA, Amardeep Jain.

He said the land would be handed over to the DMRC as soon as the residents are shifted. The removal of some constructions standing very close to the Metro line in Ballabgarh city is still to be taken up.

The trial run of the Rs 570 crore project, launched in May 2015, was conducted on August 24. The stretch has two stations — NCB and Ballabgarh.

Major cause of delay 

  • The DMRC authorities have asked HUDA (HSVP) officials to hand over a patch of 2.5 acres situated opposite the NCB (Sant Surdass) Metro station for the construction of the parking lot of the station
  • The spot, located across National Highway-2 (western side), is presently occupied by 250 shanties and the place is known as Azad Nagar 
  • Though an attempt was made to clear the constructions here, it is reported that the officials concerned were directed to rehabilitate the residents of this locality in Ashiana housing scheme before taking any action
Show comments
Show comments

Top News

View All

Indian Air force rescues 2 NRI women tourists from forest of Himachal Pradesh’s Sirmaur

Local administration warns tourists not to venture on the Churdhar track without information

56% disease burden in India due to unhealthy dietary habits

Report links consumption of processed food, excessive use of mobile phone with obesity, diabetes

Half a century after receiving Maha Vir Chakra in 1971 war, injured Navy diver who trained Mukti Bahini seeks grant of special pension

In a petition filed before the Chandigarh Bench of the AFT, 80-year old Chiman Singh, then a Leading Seaman, has sought quashing of the order issued by the authorities to deny him special pension

10-year-old Delhi boy runs food cart to support family after father’s death; businessman offers help

Sharing a video on X, Anand Mahindra extends support to the boy

Most Read In 24 Hours